Tender launched for substation projects at Chincha and Nazca

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

Private investment promotion agency (Proinversión) in Peru has launched tender notice seeking private developers for two 220/60 kV substation in Chincha and Nazca. The project includes design, financing, construction, operation, and maintenance of two 220/60 kV substation at Chincha and Nazca.

The scope of works for substation at Chincha involves:

220 Kv side: Double bus configuration with transfer disconnector. It would be made up of:
  • One (01) 100 MVA three-phase 220/60/10 kV power transformer (ONAF). Alternatively, a bank of three (03) single-phase transformers, plus a reserve unit, of 100/3 MVA each, may be installed.
  • Four (04) cells, of which two (02) are line, one (01) of the power transformer, and one (01) of bus coupling.
60 Kv side: Double bar configuration. It would be made up of:
  • Eight (08) cells, of which six (06) are line, one (01) of the power transformer, and one (01) of bus coupling.

The scope of works for substation at Nazca involves:

220 kV side: Double bus configuration with transfer disconnector. Made by:
  • One (01) 50 MVA three-phase 220/60/10 kV power transformer (ONAF).
  • Four (04) cells, of which two (02) are line, one (01) of the power transformer, and one (01) of bus coupling.
60 kV side: Double bus configuration. Made by:
  • Four (04) cells, of which two (02) are line, one (01) of the power transformer, and one (01) of bus coupling.

The deadline to submit the bids for both projects is September 23, 2020. You can find more information about this tender notice on our business opportunity page here.