Chile Launches US$16 million Lo Saldes Bridge Replacement Project in Santiago

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

Chile's Ministry of Public Works (MOP), in partnership with Costanera Norte, has begun replacing the superstructure of the Lo Saldes Bridge in Santiago, Chile.

The first phase of the Lo Saldes Bridge replacement project has commenced, marking a major infrastructure upgrade aimed at improving connectivity between the Santiago communes of Providencia, Las Condes and Vitacura. The bridge carries an average of more than 50,000 vehicles each day, making it a vital transport link in the eastern part of the capital. Construction is scheduled to continue until January 2027. During this period, the bridge's outer lanes will be closed, with traffic redirected to the central lanes to maintain access. One lane in each direction will remain open for light vehicles and public transport, while the existing restriction on trucks with more than two axles will stay in effect. Backed by an investment of more than US$16 million, the project will replace and modernise the 164-metre-long bridge, originally built in 1971, extending its service life while enhancing its structural integrity and safety standards. The works, being carried out by the concessionaire Costanera Norte, include replacing the four original metal beams with eight new high-strength beams, as well as reinforcing the abutments and piers. These improvements will restore the safety and seismic resilience of this strategic infrastructure, which connects important road corridors such as Avenida Presidente Kennedy, Costanera Norte, and the San Cristóbal Tunnel.

The construction process was planned in three sequential phases to minimize its impact on traffic flow:

  • Phase 0 included preparatory work, such as reinforcing the interior beams and adapting the piers and abutments to comply with current seismic regulations. This phase did not include any work on the bridge deck.
  • Meanwhile, Phase 1, which begins this Monday, July 27, 2026, and runs until January 2027, involves the intervention and reconstruction of the side decks through the dismantling of the existing structure, the installation of new beams, and the construction of new decks. Traffic will be maintained through the central section, with one lane in each direction.
  • Finally, Phase 2, to be carried out between January and April 2027, involves work on the central section of the bridge, including the replacement of the beams and the construction of the new central deck. During this stage, traffic will be diverted to the side decks rebuilt in the previous phase, maintaining one lane in each direction.

Due to the scale of the works and the simultaneous execution of other interventions on nearby streets and roads, episodes of greater congestion could occur in the area. According to the current schedule, the completion of all works is estimated for May 2027.

 

List of the country updates

Country updates

  • July 22, 2026

    Chile Begins Consultant Prequalification for Airport Expansion PPP Project

    The Chilean Ministry of Public Works (MOP) has launched a prequalification process for national and international consulting firms to develop the reference design for the future expansion of Arturo Me...

    Read more
  • June 23, 2026

    Chile Awards US$355 Million Ruta Pie de Monte Highway Concession in Biobío

    Chile's Ministry of Public Works (MOP) has awarded the US$355 million Ruta Pie de Monte highway concession to Sacyr Concesiones Chile SPA in the Biobío Region, Chile, to build, operate and main...

    Read more
  • June 22, 2026

    Installation of 121 Cabins Begins for Santiago's Bicentenario Cable Car

    Chile's Ministry of Public Works (MOP) has begun installing 121 passenger cabins for the Teleférico Bicentenario in Santiago, Chile. The country's first public urban cable car system represent...

    Read more
  • June 16, 2026

    MOP awards new concession for Route 5, Río Bueno-Puerto Montt section, for US$821 million

    The Chilean Ministry of Public Works (MOP), through its General Directorate of Concessions, awarded a US$821 million concession to Intervial Chile S.A. to modernize the 129-km Route 5 South between R&...

    Read more
  • May 25, 2026

    Chile Begins US$16 Million Lo Saldes Bridge Reconstruction Project

    The Chilean Ministry of Public Works (MOP) has initiated the replacement of the superstructure of the Lo Saldes Bridge in Santiago, Chile, in coordination with the Costanera Norte concessionaire, thro...

    Read more

Share this update